This created a small cubby under the stairs that we decided to name after construction supervisor Armin Bunkleman. Here he is.
Hmm... 2-1/2 weeks before we move in, we decide to make a major change in the floor plan. Originally, the main entry stairs leading from the ground floor lobby to our 2nd floor reception area was to be a wide, welcoming and inviting structure that would leave the way to the elevator (towards the back of the building) with a clear and open path.
middle of the stairs could not be removed for structural reasons, and perhaps most importantly, a large cross beam at the bottom of the stairway also had to stay.
configured grand staircase in this space in just a few short weeks!
Work continues as we get closer and closer to our move in date. Carpet arrived last Friday and is being installed now.
Taping and painting of the interior of the monitor is now complete.
Here you can see a sample of the wood being used for the frames .
The project architect was very particular about the type of wood to be used to convey a "warm Northwest flavor." White oak? Red hemlock? Only our architect knows for sure.
Mid-Autumn Moon Festival was last Friday. Seniors at Sunshine Garden Senior Day Center had a party celebrating the holiday with many yummy treats - and a work party.
Staff work hard to bring you the lastest news and happenings at CISC. We also try to share some of the stories that help keep our staff and volunteers so dedicated to the work. Support from the community has such an incredible impact on the lives of those we serve. We really couldn't do it without you!
That's what we are. Now that all the bracing is all done, we have nothing to fear in the event of an earthquake - or an eruption of Mount Rainier.
Check out all the bolts that anchor the top of the brace through the 8 8 inch thick beam.
wrench this guy's using to tighten the bolts.
After many e-mails and phone calls back an forth, we found out that we will be able to complete all the elevator work in time and that we won't have to change out the controller before we move in. Yeah!
What a luxury! Staff restrooms in designer colors!

Part of the rennovation of the building required extra support for the building through the addition of steel bracing. There are 2 sets of these huge steel bars running up from the ground through the 1st and 2nd floors up to the ceiling. 
Yesterday, all the cabinetry for the building was delivered. Via forklift! 
operational, at least for a couple of days so we can move all our cubicles (which have been stored downstairs) and drywall up for the installers to work on. Turns out there may need to be another more expensive fix before we can move in though. We'll know more next week. 
In case you haven't been by the building lately, here are some pictures of the newly installed windows. The 2 story curtain wall for the International Family Center and International Community Technology Center is the most obvisous from the parking lot.
Up in on the 3rd floor, it's almost floor to ceiling.
Kind of hard to imagine for Seattle, isn't it?
This past week, the old entrance to the building was removed then reinstalled flush with the exterior building wall so that we get an extra 10-12 feet or so as you enter the new space. Doesn't sound like much, but because it's open up to the top of the 2nd floor, it really makes for a dramatic entrance.
have the ability to remain open during regular business hours took about 2 weeks and several consultations with the window supplier, general contractor, and low voltage wiring people.
Our elevator, which has not been run in over 2 years is in need of a major upgrade. In addition to getting it going again, we're having to make it ADA accessible. This means ripping out the control panel, lowering it to wheelchair height, putting in braille, a handrail, and a phone for if it gets stuck.
Even as workers are struggling to continue work on the roof with the weather turning bad, insulation, ceiling grid, primer, and first coat of paint have gone up on parts of the interior.
With the recent rains, work on the roof has been proceeding slowly. They were supposed to be finished by Friday, but it looks like it may be another week.
As soon as the roof is done, the insulation is ready to go!
Besides having to put up with noise from saw cutting, hammering, big trucks, drilling, and general all around pounding, our future neighbors downstairs, Cathy Bank, recently opened up one morning to discover their entire office covered with a 1/2 inch of dust and debris covering everything! This was from the work being done on the roof, which, much to our dismay, impacted them significantly.
Here's what the monitor looks like now (you know, that big rectangle we cut in the roof, then pushed up 8 feet?) . They've finished sheetrocking the ceiling and sides and have put in the electrical connections for the lights.
that will go into this space. We think we can get 29 or 30 8' x 8' cubicles in here. Not only are they slightly larger than many other workspaces, they also have glass panes on the top part of the panels so there will be more light and an airier feeling - while still maintaining roughly the same amount of sound blocking.